Vaishali/Patna: The land acquisition process for the proposed industrial area in Rajapakar, Vaishali district, is progressing, with the administration aiming to hand over the remaining land by October 31.
A total of 1,234.42 acres across 11 maujas (revenue villages) is being acquired for the project. Of this, 485.51 acres across eight maujas have already been handed over to the Industrial Development Authority (IDA), Patna.
The district administration has set a deadline of October 31 to transfer possession of the remaining 748.92 acres across three maujas: Bahsi Damodar, Bahsi Saidpur and Jafarpatti.
The District Magistrate, Varsha Singh, shared the details at a press conference at his office on Thursday, stating that Rs 316 crore in compensation had been paid to approximately 3,800 landowners, known locally as raiyats.
Land Handover To Be Completed By October 31
The transfer of land to the IDA has taken place in two phases. On October 3, possession of 159.47 acres across five maujas was handed over to the authority.
On October 21, another 326.04 acres across three maujas was transferred, taking the total area handed over to 485.51 acres across eight maujas.
Officials have been instructed to complete the formalities required to transfer the remaining 748.92 acres by October 31. Once possession of the entire land parcel is handed over, the next stages of establishing the industrial area will begin.
Rs 316 Crore Paid To 3,800 Landowners
The administration has received compensation applications covering approximately 600 acres from around 4,900 landowners. Of these, approximately 3,800 have received a combined Rs 316 crore in compensation.
Verification of applications from the remaining eligible landowners and the payment process are continuing. The administration has said compensation will be disbursed to eligible applicants in accordance with established rules.
Some landowners have raised objections over compensation rates and the structure of payments. A district-level committee has been formed to examine the objections and submit a report. Further action will be taken according to the applicable rules based on the committee’s findings.
Land Allocation To Industries To Follow
After the remaining land is transferred, the IDA will conduct surveys and complete the necessary procedures. The relevant department will then begin the process of allocating land to industries.
The proposed industrial area is expected to provide land for new industrial units in Vaishali district, potentially encouraging investment and creating employment opportunities locally.