Patna: The Bhagalpur District Magistrate has taken a firm stance over delays in land acquisition and compensation payments for the Goradih Industrial Corridor and other important projects in the district.
The District Land Acquisition Officer has been asked to submit an explanation within 24 hours. The DM has warned that if the response is not satisfactory, a proposal for disciplinary action will be sent to the concerned department.
The pending land acquisition cases were supposed to be heard every two days, while compensation payments were required to be completed within three months of the declaration of the award.
Pending Cases Were to Be Heard Every Two Days
In the show-cause notice, the District Magistrate stated that progress on the Goradih Industrial Corridor and other key projects is being regularly reviewed at the Chief Minister’s level.
Timely completion of these projects requires the speedy resolution of land acquisition disputes and the payment of compensation to affected landowners.
The administration had specifically directed that pending land acquisition cases related to the Goradih Industrial Corridor be heard at intervals of every two days. The aim was to resolve land-related disputes quickly and ensure that the compensation process was completed without delay.
Compensation Payments Still Pending Three Months After Award
The DM noted that all pending and payable compensation amounts were supposed to be disbursed within three months of the declaration of the award.
However, the payment process has reportedly remained delayed despite these instructions.
The District Magistrate described the delay as a sign of negligence, arbitrary conduct and disregard for higher-level directions. The issue prompted the administration to seek an explanation from the District Land Acquisition Officer.
Disciplinary Action May Follow Unsatisfactory Response
The officer has been directed to clearly explain the reasons behind the delay in compensation payments. A detailed report on the status of pending hearings and compensation disbursements has also been sought.
The DM has made it clear that an unsatisfactory explanation could lead to a recommendation for disciplinary action against the officer to the concerned department.
Land acquisition and compensation payments are crucial to the progress of the Goradih Industrial Corridor. The administration’s intervention is expected to push the resolution of pending cases and speed up the process.