What’s Changing At Patna Zoo Metro Station? 4 TBMs To Start Digging In November

The design of the under-construction Patna Zoo Metro station is being revised, while four tunnel boring machines are scheduled to begin underground tunnelling in November.

Staff Reporter by Staff Reporter
September 8, 2026
in Infrastructure, Patna
Reading Time: 2 mins read
Traffic and construction work near Akashvani Metro station in Patna
0
SHARES
52
VIEWS
Share on FacebookShare on Twitter

Patna: The design of the under-construction Patna Zoo Metro station is set to change as construction moves ahead on the underground section of Patna Metro’s Corridor 1.

A meeting on the proposed design changes was held on Monday under the chairmanship of Patna Metro Rail Corporation managing director Sandeep Kumar R Pudkalakatti. Officials from the Delhi Metro Rail Corporation (DMRC) and other agencies associated with the project attended the meeting and provided suggestions on the revised design.

Officials said four tunnel boring machines (TBMs) will be lowered from a metro shaft near Patna Zoo in November to begin tunnelling work.

Two TBMs To Tunnel Towards Patna Junction

Two of the four TBMs will move eastwards from the shaft near Patna Zoo.

The machines will construct the up and down tunnels towards Patna Junction. This work is expected to accelerate construction of the underground section of Corridor 1.

The tunnels will form part of the planned underground alignment between Patna Junction and Rukanpura.

Two TBMs To Move Towards Rukanpura

The remaining two TBMs will move westwards towards Rukanpura station.

They will construct the up and down tunnels on this section. Preparatory work for deploying the machines is being carried out.

The simultaneous deployment of four TBMs is expected to give a significant push to underground construction.

Station Design Under Review

The proposed changes to the Patna Zoo station design were discussed during Monday’s meeting.

Officials from DMRC and other agencies reviewed the design and offered suggestions. The revised plan is being considered as part of the ongoing preparations for underground construction in the area.

Focus On Speed, Quality And Safety

Project agencies have been directed to accelerate construction while maintaining prescribed quality standards.

Officials were also asked to resolve construction-related issues through coordination between the agencies involved.

The meeting also emphasised compliance with safety requirements during construction, particularly as underground work is expanded.

Corridor 1 To Have 10.54 Km Underground Section

Patna Metro Corridor 1 has a total planned length of 17.93 km.

Of this, 10.54 km will be underground, while 7.39 km will be elevated.

The first underground section will connect Patna Junction and Rukanpura. A subsequent phase is planned between Patna Junction and Mithapur.

Elevated Work Between Patliputra And Danapur

Corridor 1 also includes a 7.39-km elevated section between Patliputra and Danapur.

Construction work on the elevated section is progressing. An elevated section between Khemni Chak and Mithapur is also under construction.

Metro operations on the Khemni Chak-Mithapur elevated section are targeted to begin in June 2027.

Corridor 2 Has Underground And Elevated Sections

Patna Metro’s Corridor 2 has a planned length of 14.55 km. Its underground section will cover 7.92 km, with the remaining stretch planned as elevated.

The elevated section currently in operation includes ISBT, Zero Mile, Bhoothnath and Malahi Pakri stations.

The planned underground section includes Rajendra Nagar, Moinul Haq Stadium, Patna University, PMCH, Gandhi Maidan, Akashvani and Patna Junction.

Operations on the underground section of Corridor 2 are targeted to begin in 2028.

The planned deployment of four TBMs in November is expected to mark a major step in Patna Metro’s underground construction, particularly along the Patna Junction-Rukanpura section.

Tags: Infrastructuremetro constructionPatnaPatna MetroPatna NewsPatna Zoourban transport

Related Posts

representative image of the proposed Parsa-Sampatchak four-lane road in Patna
Infrastructure

Patna’s Parsa-Sampatchak Four-Lane Road: Rs 330.24 Crore Project To Widen 6.8 Km Stretch

September 28, 2026
Representative AI Generated image of a proposed integrated commercial hub with parking and vending facilities in Patna
Infrastructure

Why PMC Is Building 15 Hubs In Patna: Rs 261.84 Crore Plan Covers Parking, Vending And Commercial Spaces

September 28, 2026
Patna Sees Twin Protests As Farmers, Workers And Students Take To Streets
Patna

Patna Sees Twin Protests As Farmers, Workers And Students Take To Streets

September 28, 2026
Next Post
Ganga river flowing at an elevated level in Patna during the flood situation

Ganga-Punpun Levels Fall In Patna—So Why Is The Flood Threat Still Not Over?

Representational image of a greenfield expressway planned to connect 13 districts across Bihar

Bihar’s New Expressway Will Connect 13 Districts—But Patna Has A Different Link

Patliputra University building in Patna

PPU Makes Placement Cells Mandatory In All Colleges To Boost Student Jobs

Instagram

  • Awadhesh Narayan Singh has resigned as Chairman of the Bihar Legislative Council. JD(U)’s Ramvachan Rai is among the names being discussed for the post.

#BiharPolitics #BiharNews #LegislativeCouncil #JD(U) #PatnaPress
  • Congress workers staged a protest in Patna against the Special Intensive Revision (SIR) of electoral rolls, raising concerns over the voter-list revision process.

During the protest, party workers marched from the district Congress office and raised slogans against the central government and Election Commission. Effigies representing Prime Minister Narendra Modi, Union Home Minister Amit Shah and Chief Election Commissioner Gyanesh Kumar were also burnt.

Congress leaders said they have raised concerns over voter verification and the possible impact of the SIR exercise on voters’ rights. The party has said its protests against the process will continue.

#SIR #CongressProtest #PatnaNews #BiharNews
  • A protest by several student organisations at Patna’s Dak Bungalow Chowk turned tense as demonstrators marching from Gandhi Maidan towards Raj Bhavan tried to cross police barricades.

Police used water cannons and light force after a scuffle broke out between protesters and personnel. Demonstrators were seen raising slogans and climbing barricades amid the water cannon spray.

The protesters raised several demands, including concerns over SIR, action against Chief Election Commissioner Gyanesh Kumar, opposition to land acquisition for townships and demands for adequate assistance for flood-affected people. Workers’ and farmers’ organisations also participated in the protest.

#PatnaNews #StudentProtest #BiharNews #DakBungalow
  • Neha Jha has been granted regular bail by Samastipur Excise Court-2 in the liquor seizure case. Ishan Kumar, the other accused, remains in judicial custody.

#Samastipur #BiharNews #RailwayNews #PatnaPress #Bihar
  • The Parsa-Sampatchak road is set for a major widening project, with 6.8 km planned to be developed into a four-lane corridor. Land acquisition has begun, while construction is expected to gain pace from November.

#PatnaNews #BiharNews #RoadDevelopment #Patna #PatnaPress
  • PMC has proposed 15 integrated civic and commercial hubs across Patna with an estimated investment of Rs 261.84 crore. The plan includes organised vending spaces, parking facilities, commercial complexes and community infrastructure across six administrative circles.

#Patna #PatnaNews #PMC #BiharNews #PatnaPress
  • Bihar’s Sankalp Portal is being developed as a central digital platform to monitor government schemes, announcements, cabinet decisions and development projects. The system will also track progress under the 100-day report card.

#BiharNews #BiharGovernment #DigitalGovernance #SankalpPortal #PatnaPress
  • Girls account for more than 60% of children reported missing in Bihar, according to figures cited by Bihar Police. Authorities are using Mission Vatsalya and special operations to trace, recover and rehabilitate missing children.

#BiharNews #ChildProtection #MissionVatsalya #BiharPolice #PatnaPress
  • Gold and silver prices declined on September 28, with 24-carat gold at Rs 1,48,048 per 10 grams and silver at Rs 2.23 lakh per kg. Patna’s 24-carat gold rate stood at Rs 1,50,220.

#GoldPrice #SilverPrice #PatnaNews #GoldRate #PatnaPress
Bihar Power Distribution To Embrace Digital And Smart Technologies By 2030: NBPDCL MD

Bihar Power Distribution To Embrace Digital And Smart Technologies By 2030: NBPDCL MD

by Aditi Srivastava
September 28, 2026
0

India is working towards a modern and digitally enabled power distribution system by 2030, with Bihar seeking to apply global...

Bihar Legislative Council Chairman Post Likely To Go To JD(U) As Awadhesh Narayan Singh Resigns

Bihar Legislative Council Chairman Post Likely To Go To JD(U) As Awadhesh Narayan Singh Resigns

by Aditi Srivastava
September 28, 2026
0

Awadhesh Narayan Singh resigned as Chairman of the Bihar Legislative Council on September 28, with JD(U) leader Ramvachan Rai emerging...

Neha Jha Granted Bail In Samastipur Liquor Seizure Case

Neha Jha Granted Bail In Samastipur Liquor Seizure Case

by Aditi Srivastava
September 28, 2026
0

Neha Jha has been granted regular bail nearly 24 days after being sent to judicial custody in the liquor seizure...

representative image of the proposed Parsa-Sampatchak four-lane road in Patna

Patna’s Parsa-Sampatchak Four-Lane Road: Rs 330.24 Crore Project To Widen 6.8 Km Stretch

by Priyani Pandey
September 28, 2026
0

The Rs 330.24 crore Parsa-Sampatchak road project will convert a 6.8-km stretch into a four-lane road and is expected to...

Bihar Power Distribution To Embrace Digital And Smart Technologies By 2030: NBPDCL MD
Bihar

Bihar Power Distribution To Embrace Digital And Smart Technologies By 2030: NBPDCL MD

by Aditi Srivastava
September 28, 2026
0

India is working towards a modern and digitally enabled power distribution system by 2030, with Bihar seeking to apply global...

Read moreDetails
Bihar Legislative Council Chairman Post Likely To Go To JD(U) As Awadhesh Narayan Singh Resigns

Bihar Legislative Council Chairman Post Likely To Go To JD(U) As Awadhesh Narayan Singh Resigns

September 28, 2026
Neha Jha Granted Bail In Samastipur Liquor Seizure Case

Neha Jha Granted Bail In Samastipur Liquor Seizure Case

September 28, 2026
representative image of the proposed Parsa-Sampatchak four-lane road in Patna

Patna’s Parsa-Sampatchak Four-Lane Road: Rs 330.24 Crore Project To Widen 6.8 Km Stretch

September 28, 2026
Representative AI Generated image of a proposed integrated commercial hub with parking and vending facilities in Patna

Why PMC Is Building 15 Hubs In Patna: Rs 261.84 Crore Plan Covers Parking, Vending And Commercial Spaces

September 28, 2026

Recent Posts

  • Patna Women’s College Hosts Delhi Lieutenant Governor Taranjit Singh Sandhu For Student Interaction
  • Bihar Power Distribution To Embrace Digital And Smart Technologies By 2030: NBPDCL MD
  • Bihar Legislative Council Chairman Post Likely To Go To JD(U) As Awadhesh Narayan Singh Resigns
  • Neha Jha Granted Bail In Samastipur Liquor Seizure Case
  • Patna’s Parsa-Sampatchak Four-Lane Road: Rs 330.24 Crore Project To Widen 6.8 Km Stretch
Bihar Power Distribution To Embrace Digital And Smart Technologies By 2030: NBPDCL MD

Bihar Power Distribution To Embrace Digital And Smart Technologies By 2030: NBPDCL MD

by Aditi Srivastava
September 28, 2026
0

India is working towards a modern and digitally enabled power distribution system by 2030, with Bihar seeking to apply global...

Bihar Legislative Council Chairman Post Likely To Go To JD(U) As Awadhesh Narayan Singh Resigns

Bihar Legislative Council Chairman Post Likely To Go To JD(U) As Awadhesh Narayan Singh Resigns

by Aditi Srivastava
September 28, 2026
0

Awadhesh Narayan Singh resigned as Chairman of the Bihar Legislative Council on September 28, with JD(U) leader Ramvachan Rai emerging...

Neha Jha Granted Bail In Samastipur Liquor Seizure Case

Neha Jha Granted Bail In Samastipur Liquor Seizure Case

by Aditi Srivastava
September 28, 2026
0

Neha Jha has been granted regular bail nearly 24 days after being sent to judicial custody in the liquor seizure...

representative image of the proposed Parsa-Sampatchak four-lane road in Patna

Patna’s Parsa-Sampatchak Four-Lane Road: Rs 330.24 Crore Project To Widen 6.8 Km Stretch

by Priyani Pandey
September 28, 2026
0

The Rs 330.24 crore Parsa-Sampatchak road project will convert a 6.8-km stretch into a four-lane road and is expected to...

Recent News

  • Patna Women’s College Hosts Delhi Lieutenant Governor Taranjit Singh Sandhu For Student Interaction
  • Bihar Power Distribution To Embrace Digital And Smart Technologies By 2030: NBPDCL MD
  • Bihar Legislative Council Chairman Post Likely To Go To JD(U) As Awadhesh Narayan Singh Resigns
  • Home
  • Patna
  • Bihar
  • Politics
  • Campus Buzz
  • Crime
  • Nation
  • World
  • Infra
  • Business
  • Lifestyle
  • Opinion
  • About us

© 2026 PatnaPress.com

No Result
View All Result
  • Home
  • Patna
  • Bihar
  • Politics
  • Campus Buzz
  • Crime
  • Nation
  • World
  • Infra
  • Business
  • Lifestyle
  • Opinion
  • About us

© 2026 PatnaPress.com