Patna Metro’s First Interchange Station Delayed, Now Set To Open By December
Khemnichak station will open only after work on both the Malahi Pakri and Mithapur routes is completed, while several underground ...
Khemnichak station will open only after work on both the Malahi Pakri and Mithapur routes is completed, while several underground ...
Construction at Patna Metro’s Rukanpura station is gaining pace, with reinforcement steel cages being installed for the underground diaphragm wall ...
: Land clearance has begun around Patna Junction for a planned underground metro interchange that will connect two corridors and ...
A roughly two-metre section of road in front of Natya Kala Bhavan will be temporarily blocked, while both lanes between ...
Patna Metro Rail Corporation Limited has proposed procuring three six-coach trainsets, adding 18 coaches to the operational fleet as passenger ...
Two TBMs will tunnel towards Patna Junction and two towards Rukanpura as work on Patna Metro’s underground Corridor 1 gathers ...
Bihar Urban Development and Housing Minister Nitish Mishra reviewed Patna Metro’s progress and directed officials to speed up construction and ...
Patna Metro aims to begin operations between ISBT and Patna Junction by 2028, with the first 7.5km underground tunnel between ...
Patna Metro is stepping up construction and capacity plans, with six-coach trains being procured as work advances on the Mithapur-Khemnichak ...
The Bihar government has approved Rs 628.32 crore for the Patna Metro Rail project, providing fresh funding for core construction ...